Construction of Retaining Wall Near Biotechnology Building to Commence on Wednesday, June 15

Summary of disruption: The Electrical Infrastructure Upgrade (EIU) project contractor will build a retaining wall near the Biotechnology Building (Building 4) starting on Wednesday, June 15. The work will be performed on weekdays from approximately 6:30 a.m. to 4 p.m. The wall is expected to be completed by Wednesday, July 6.

Reason for disruption: The retaining wall will provide protection to electrical switches close to a hillside near the building.

How does this affect me? The construction of the wall may produce intermittent noise. Access to the building and parking in stalls along Camphor Lane will not be impacted.

What do I need to do? Please share this information with others in the building who may have not received this message.

For any questions or more information, please contact: Bruyn Bevans, Senior Project Manager, at (909) 979-5517 or Chris Norris, lead electrician, at (909) 238-6831 or (909) 997-6467.