The Compass

Installation of Electrical Meter Conduits at Kellogg West Addition to Start on Friday, Oct. 1

Summary of Disruption: The Electrical Infrastructure Upgrade (EIU) Project contractor will begin installation of electrical meter conduits at the Kellogg West Addition (Building 76) starting on Friday, Oct. 1. The work will be performed on weekdays from approximately 7 a.m. to 3:30 p.m. and is expected to be completed by Friday, Oct. 8.  

Reason for Disruption: Allow contractor crews to start installing conduits for the new electrical system.

How does this affect me? Access to the Kellogg West Addition will not be impacted.

What do I need to do? Please share this information with others who may have not received this message.

For any questions or more information, please contact: Bruyn Bevans, Senior Project Manager, at (909) 979-5517 or Chris Norris, lead electrician, at (909) 238-6831 or (909) 997-6467.