The Compass

Second Stage of Trenching in Parking Lot J to Commence on Tuesday, May 18

Summary of Disruption: The Electrical Infrastructure Upgrade (EIU) Project contractor will trench a second section of Parking Lot J starting on Tuesday, May 18. The work will be performed on weekdays from approximately 7 a.m. to 3:30 p.m. The site will be fenced off and the work is expected to be completed in early June.   

Reason for Disruption: Allow EIU contractor crews to start installing the new electrical system.    

How does this affect me? Access to Parking Lot J is available. The upper section of the lot will be impacted. 

What do I need to do? Drivers and pedestrians are urged to use caution when approaching the work area. Please share this information with others who may have not received this message.

For any questions or more information, please contact: Bruyn Bevans, Senior Project Manager, at (909) 979-5517 or Chris Norris, lead electrician, at (909) 238-6831 or (909) 997-6467.