Trenching in Sidewalk Near Darlene May Gymnasium to Begin on Monday, July 12

Summary of disruption: The Electrical Infrastructure Upgrade (EIU) Project contractor will trench in the sidewalk and green space near Darlene May Gymnasium (Building 41) starting on Monday, July 12. The work will be performed on weekdays from approximately 7 a.m. to 3:30 p.m. The work area will be fenced off and installation is expected to be completed by Monday, July 26. 

Reason for Disruption: Allow EIU contractor crews to start installing the new electrical system.

How does this affect me? Sections of sidewalk near the gymnasium will be barricaded.

What do I need to do? Drivers of campus vehicles and pedestrians are urged to use caution when approaching the work area. Please share this information with others who may have not received this message.

For any questions or more information, please contact: Bruyn Bevans, Senior Project Manager, at (909) 979-5517 or Chris Norris, lead electrician, at (909) 238-6831 or (909) 997-6467.