Summary of Disruption: Work crews will begin trenching in the green area south of the College of Business Administration starting on Tuesday, Sept. 1. The digging will occur weekdays from approximately 7 a.m. to 3:30 p.m. The trenching is scheduled to be completed in approximately two weeks. A construction fence will be erected around the work area.

Reason for Disruption: Allow contractor crews to start the first phase of trenching as part of the Electrical Infrastructure Upgrade Project that is underway.   

How does this affect me? The work area will be fenced off. Access to the College of Business Administration buildings will not be affected.

What do I need to do? Proceed with caution when approaching the work areas. Please share this information with others who may have not received this message.

For any questions or more information, please contact: Chi Kwan Fong, project manager, at (909) 378-0399 or Ext. 4062, and Chris Norris, lead electrician, at (909) 238 6831 or Ext. 3044.